SLS is delayed again by a hydrogen leak but repair allows another go…but when?

by | Sep 5, 2022 | Launches, NASA, Seradata News, SLS

Having had its previous launch attempt on 29 August scrubbed by an engine temperature sensor issue, a second attempt to launch the giant SLS rocket carrying the Orion capsule on an uncrewed Artemis I test flight was delayed again on 3 September. This time it was a large hydrogen leak that did the damage.

The launch was supposed to have taken place at 1817 GMT or in the two-hour window afterwards. However, a leak was detected from the seal of the hydrogen propellant line coupling the ground to the core stage. Two attempts were made to fix the seal, firstly by allowing it to warm up before restarting the flow, and then using helium pressurant to try to force it into its seating position. Eventually the decision was made to scrub the launch for a second time after neither technique worked. An earlier hydrogen vent valve leak in a different area was deemed small enough to allow the 29 August original launch attempt to go forward, albeit that the engine-sensor issue later scuppered it. However, this latest launch leak was deemed to create too much of a flammability risk.

The wait goes on: SLS stands forlornly on Pad 39B at the Kennedy Space Center on 3 September. Courtesy: NASA

Update on 22 September 2022: After the fault, it was decided that instead of returning the rocket assembly to the Vehicle Assembly Building (VAB), the change of the suspect seals would be attempted on the pad. This was successfully done and a full propellant tanking and pressurisation test was performed on both main stages on 21 September. The cause of the leak remains mysterious. A “witness” mark on one of the seals suggested that debris might have caused a fluid escape channel, but no debris was ever found. As it was, despite the new seals on the connectors, a hydrogen leak remained. NASA says the hydrogen leak during the pre-pressurisation test on the core-stage fuel tank was in a 4-inch bleed line quick-disconnect fitting. This is a separate line from the 8-inch fill and drain connector that was the original problem. With a detected hydrogen concentration in the pad area of just four per cent, this was within the five per cent limit to attempt a flight. NASA was loath to give up its rescheduled launch on 27 September, given that any further delay would have required a further extension/waiver for the certification of the batteries for the on-board destruct system by the range safety authorities of the US Space Force.

Update on 24 September 2022: Tropical Storm Ian forced NASA’s hand into delaying launch. The 27 September date was given up despite a waiver on the certification of the destruct system’s batteries. NASA was left having to decide whether to send the SLS back into the VAB for its own protection from high winds etc.

Update on 26 September 2022: After Hurricane Ian messed up the latest launch plan, NASA made the decision to roll the SLS assembly back into the VAB for its protection. Thus, late October may be the next possible launch date for Artemis 1. Other sources suggest that November is more likely due to the need to change flight termination system batteries which would have expired.

About Seradata

Seradata produces the renowned Seradata database. Trusted by over 100 of the world’s leading Space organisations, Seradata is a fully queryable database used for market analysis, failure/risk assessment, spectrum analysis and space situational awareness (SSA).

For more information go to https://www.seradata.com/product/

Related Articles

Categories

Archives

Tags

nasaspacexecoreviewsissesaArianespacevideochinaFalcon 9v1.2FT Block 525virgin galacticULAfalcon 9evaRoscosmosspacewalkDGAaviation weekBlue OriginInternational Space StationaresIGTsoyuzRocket LabBeidouawardsStarlinkspaceAirbus DSboeingSatellite broadcastingrussiamoonOneWebISROCargo Return VehiclemarsblogresearchspaceshiptwoorionjaxamarsimpactdelayhyperbolaEutelsatdemocratrocketlunarhypertextobamagoogle lunar prizelaunchVegathales alenia spaceSESconstellationtourismbarack obamafiguresnorthspaceflightIntelsatnode 2fundedRaymond Lygo2009Lockheed MartinExpress MD-2Elon MuskAtlas Vromess2dassault aviationsstlaviationLucy2008wk2ukradiosuborbitaltestmissiledocking portexplorationAriane 5 ECAVirgin OrbitinternetSLSLong March 2D/2ElectronNorthrop GrummanChina Manned Space Engineeringsts-122Ariane 5missile defensenewspapercotsgalileospace tourismflight2010Long March 4CspaceportExpress AMU 1buildspace stationaltairsoyuz 2-1aProton Minternational astronautical congressshuttlespace shuttleAriane 6scaled compositesIntelsat 23European Space AgencyLauncherOneCosmoshanleybudgetrulesnew yorkatvVietnamshenzhoucongressMojaveboldennew shepardLong March 2CInmarsatOrbital ATKcnesiaclunar landerGuiana Space CenterApollolawsUS Air ForceSpace Systems/LoralUK Space AgencyLong March 4BKuaizhou 1AkscILSprotondarpaTalulah RileyElectron KSFalcon 9v1.2 Block 5Vega CNorth KoreaeuSkylonAstriumpicturebaseusaastronautdragonlanderfiveeventTelesatSSLAprilSNC50thinterviewLong MarchSea LaunchfalconWednesdaycustomerlinkatlantissuccessor

Stay Informed with Seradata

Stay informed on the latest news, insights, and more from Seradata by signing up for our newsletter.